All-Weather Equipment Access for Pertamina Oil Field in High Rainfall Zone
Approach
EcoMatPro® supported a critical workover and field enhancement project in one of Sumatera’s highest rainfall areas. Lack of infrastructure maintenance had left well pad access impassable, threatening production for National Oil Company, Pertamina. With large-scale civil works deemed too costly, EcoMatPro conducted a detailed site assessment and implemented the modular ECM-70 matting solution. Using a Leapfrog Zero equipment footprint installation strategy. This approach enabled reliable, all-weather access for rigs, equipment, and personnel while minimizing environmental impact and eliminating the need for heavy construction.
Integrated Matting System Deployed
- ECM-70 Gripper: Provided robust access and support for all equipment
- ECM-30: Delivered hard standing areas, supporting general site and camp operations
- ECM-70: Delivered high load-bearing capacity directly under drilling rigs and heavy equipment
The three EcoMatPro ground protection matting solutions were rotated between 26 sites to maintain a continuous operations
Project Outcomes
- 35 weeks of uninterrupted access to multiple well pads
- Zero matting repair costs incurred by the client
- Avoided large-scale civil works, saving time and capital
- Achieved production restoration goals with minimal delays
- Delivered a low-impact, sustainable access solution under extreme weather conditions